Petroleum Development Oman
1,600 Person Hours
Human Factors Engineering Consultancy
Apr-2013
Our PDO approved Human Factors Engineering Facilitator & Scribe conducted a design review for assurance that the project design was according to PDO DEPs. A Human Factors Engineering report with design change recommendations was produced for PDO approval....
Petroleum Development Oman
2,000 Person Hours
Alarm Management System
Apr-2014
The application software on server and clients was upgraded....
Petroleum Development Oman
1,900 Person Hours
Human Factors Engineering Consultancy
Mar-2013
Our PDO approved Human Factors Engineering Facilitator & Scribe conducted a design review for assurance that the project design was according to PDO DEPs. A Human Factors Engineering report with design change recommendations was produced for PDO approval....
Petroleum Development Oman
9,700 Person Hours
Engineering Consultancy
Jun-2013
Follow PDO specific DCADA System Hardening measures for all Control Systems Servers, Operator and Engineering Workstations at site. This included recording all systems and software attributes including licences and installed software and conducting intrusion impact awareness training with all users in the PDO assets....
Petroleum Development Oman
700 Person Hours
Engineering Consultancy
Dec-2012
Our PDO approved TA2 consultant participated in a Pre Start-up Audit (PSUA) for assurance that the project design was according to PDO DEPs for the Control, Instrumentation and Automation of the project....
Petroleum Development Oman
2,000 Person Hours
Human Factors Engineering Consultancy
Nov-2012
Our PDO approved Human Factors Engineering Facilitator & Scribe conducted a design review for assurance that the project design was according to PDO DEPs. A Human Factors Engineering report with design change recommendations was produced for PDO approval....
Petroleum Development Oman
1,400 Person Hours
Human Factors Engineering Consultancy
Sep-2012
Our PDO approved Human Factors Engineering Facilitator & Scribe conducted a design review for assurance that the project design was according to PDO DEPs. A Human Factors Engineering report with design change recommendations was produced for PDO approval....
Petroleum Development Oman
1,800 Person Hours
Engineering Consultancy
Sep-2012
Consult with client and establish the project plan and determine manning levels based on systems, units and operational requirements at each project phase and producing a manning strategy....
Petroleum Development Oman
800 Person Hours
Engineering Consultancy
Jul-2013
Our PDO approved TA2 consultant participated in a design review for assurance that the project design was according to PDO DEPs for the Control, Instrumentation and Automation of the project....
Petroleum Development Oman
2,500 Person Hours
Engineering Consultancy
May-2012
Consult with client and establish the project plan and comparable manpower utilisation from similar project of this size to establish manning levels at each stage of engineering, construction, commissioning, Start-up, operations and maintenance. These discipline manning levels were then used to identify competencies required at each project phase, current available staff competencies gap assessme...
Petroleum Development Oman
2,500 Person Hours
Alarm Management System
Jun-2013
Application software modifications to configure a single OPC connector to the remote Marmul production station. Alarms were checked with daily, weekly and KPI reports automatically sent to the local maintenance co-ordinator and Alarms Management Team....
Petroleum Development Oman
7,200 Person Hours
Alarm Management Facilitation, Rationalisation or Implementation
Feb-2013
PDO engaged us to implement the previously rationalised alarms by liaising with the systems vendor....
CC Energy Development
3,700 Person Hours
Detailed Design
Sep-2011
Interface Management during design stage ensuring information provided by vendors to sufficient to construct and commission and identifying issued that require resolution by vendors and CCED the owner....
Petroleum Development Oman
21,700 Person Hours
Alarm Management Facilitation, Rationalisation or Implementation
Nov-2011
PDO engaged us to implement the previously rationalised alarms by liaising with the systems vendor....
Petroleum Development Oman
2,100 Person Hours
Alarm Management System
Jun-2011
Dell Server Hardware sizing was done based on future alarms connections to the ProcessVue application software. The Systems was installed in Muscat at Minal Fahal. The application software was installed and configured for a single OPC connector to the remote Qarn Alum production station. Alarms were checked with daily, weekly and KPI reports automatically sent to the local maintenance co-ordina...