• Oman's Future, Engineered Today

PDO Birba Control Systems Upgrade FEED

PDO decided to upgrade the old Birba Cluster and started with FEED through Imtech and WPAI for PDO. Abalto was awarded the FEED as System Integrator (SI) for the Automation, Control & Instrumentation for the Control and Safety Systems upgrade. We developed a detailed FEED for the upgrade of the legacy DCS and IPS systems by Honeywell and Yokogawa to a new Emerson DeltaV DCS system to examine the best options available and establish the best execution methodology for the upgrade along with a full bill of materials and cost estimates.
  • Client

    Petroleum Development Oman

  • Person Hours

    84,600 Person Hours

  • Primary Service Category

    Front End Engineering & Design

  • Date

    Mar-2015

Project Description

PDO decided to upgrade the old Birba Cluster and started with FEED through Imtech and WPAI for PDO. Abalto was awarded the FEED as System Integrator (SI) for the Automation, Control & Instrumentation for the Control and Safety Systems upgrade. We developed a detailed FEED for the upgrade of the legacy DCS and IPS systems by Honeywell and Yokogawa to a new Emerson DeltaV DCS system to examine the best options available and establish the best execution methodology for the upgrade along with a full bill of materials and cost estimates.

Technical Details & Specifications


Old Yokogawa FastTools SCADA
Old Yokogawa Stardom FCS
Old Yokogawa ProSafe IPS
Old Honeywell DCS
Old Relay Control Panels
New Emerson DeltaV DCS
New HIMA IPS

Deliverables


Site Survey
As Built Documentation
Front End Engineering & Design
Philosophies
Specifications
Bill of Materials
Project Planning
Project Cost Estimates